Let job set J={J 1 , J 2 , J 3, J 4 }, J i =(r i , c i , d i ),
Let job set J={J1, J2, J3, J4}, Ji=(ri, ci, di), where ri , ci, and di are the arrival time, the worst case execution cycles, and deadline for Ji, respectively. Let J1=(1, 3, 16), J2=(4, 4, 24), J3=(12, 5, 22), J4=(0, 2, 40) be scheduled on an ideal DVS processor according to EDF. Find the voltage schedule that can minimize the dynamic energy consumption to complete these jobs in time.