Lets assume a 12-month railway project that is planned to spend $3M per month for a total budget at completion (BAC) of $36M. The project
Lets assume a 12-month railway project that is planned to spend $3M per month for a total budget at completion (BAC) of $36M. The project is 2 months along and according to the planned vs. actual cost figures is underspent by 50%. We could assume therefore that the project is going well because its costing less than planned. But after 2 months of work, 10 % of work has been completed