LetXbe the number of weeks required to complete the development of product specifications, and letYbe the number of weeks required to complete the design of
LetXbe the number of weeks required to complete the development of product specifications, and letYbe the number of weeks required to complete the design of the manufacturing process. Based on experience, you estimate the following probability distribution for the first step:
Weeks(X) 1 2 3
Probability 0.3 0.5 0.2
For the second step, your estimated distribution is
Weeks(Y) 1 2 3 4 5
Probability 0.1 0.15 0.4 0.3 0.05
The cost per week for developing product specifications is$8000,while the cost per week for designing the manufacturing processis $30,000.
Calculate the standard deviation of the cost for each of the two activities using the rules for variances. The standard deviation foris0.7and for is 1.0235.
Round to two decimal places when necessary.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started