Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is
Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is completed. For the first quarter of the year, the following data were reported: |
Inspection time | 0.4 | days |
Process time | 2.5 | days |
Wait time | 15.5 | days |
Queue time | 4.5 | days |
Move time | .5 | days |
Required: | |
1. | Compute the throughput time. (Round your answer to 1 decimal place.) |
2. | Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your intermediate calculations to 1 decimal place and final answer to 2 decimal places.) |
3. | What percentage of the throughput time was spent in nonvalue-added activities? |
4. | Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.) |
5. | If by using Lean Production all queue time can be eliminated in production, what will be the new MCE? (Do not round intermediate calculations. Round your answer to 2 decimal places.) |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started