Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is

Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is completed. For the first quarter of the year, the following data were reported:

Inspection time 0.4 days
Process time 2.5 days
Wait time 15.5 days
Queue time 4.5 days
Move time .5 days

Required:
1.

Compute the throughput time. (Round your answer to 1 decimal place.)

2.

Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your intermediate calculations to 1 decimal place and final answer to 2 decimal places.)

3.

What percentage of the throughput time was spent in nonvalue-added activities?

4.

Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.)

5.

If by using Lean Production all queue time can be eliminated in production, what will be the new MCE? (Do not round intermediate calculations. Round your answer to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Aviation Tax IRS Audit Techniques Guide

Authors: Internal Revenue Service

1st Edition

1304131696, 978-1304131690

More Books

Students also viewed these Accounting questions