Question
Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is
Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is completed. For the first quarter of the year, the following data were reported:
Inspection time 0.5 days
Process time 2.8 days wait time 16.0 days
Que time 4.0 days
Move time 0.7 days
Compute the throughput time_____days
Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your answer to 2 decimal places.)
What percentage of the throughput time was spent in non-value-added activities?____% |
Compute the delivery cycle time ____days
If by using Lean Production all queue time can be eliminated in production, what will be the new MCE? (Round your answer to 2 decimal places.)_____
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started