Question
Livernonions Industries uses a kanban system to manage production of the BR-549 subassembly. In an eight-hour day, they use 1200 units and use containers that
Livernonions Industries uses a kanban system to manage production of the BR-549 subassembly. In an eight-hour day, they use 1200 units and use containers that can hold 50 units each. It takes 120 minutes to fill and move a container of parts to the right place on the BR-549 line that is currently rated at a 25% safety factor. How many production hours of inventory are needed?
Group of answer choices
- 375
- 2.4
- 2.5
- 7.5
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the production hours of inventory needed in a kanban system with a safety factor follow ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Cost Management Accounting And Control
Authors: Don R. Hansen, Maryanne M. Mowen, Liming Guan
6th Edition
324559674, 978-0324559675
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App