Long-Term Construction Contracts
Forman Company has contracted to build a dam over a period of 4 years for $3,000,000. Information relating to the performance of the contract is summarized as follows:
Contract price | 3000000 | | | |
| 2013 | 2014 | 2015 | 2016 |
Constructions costs incurred during yr | 300000 | 1100000 | 863000 | 837000 |
Estimated costs to complete | 2200000 | 1400000 | 837000 | 0 |
Billings during the year | 280000 | 870000 | 1030000 | 820000 |
collections during the year | 270000 | 875000 | 1010000 | 845000 |
Required:
If an amount is zero, enter "0".
Prepare the relevant sections of the ending balance sheet for 2015 under the percentage-of-completion method.
|
|
|
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
Provision for loss on contract | | | | | |
| | | | |
| | | | |
| | | | |
Prepare the relevant sections of the ending balance sheet for 2013 under the completed-contract method.
|
Ending Balance Sheet (partial) | |
|
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
Excess of costs over related billings | | | | | |
Prepare the relevant sections of the ending balance sheet for 2014 under the completed-contract method.
|
Ending Balance Sheet (partial) | |
|
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
Excess of costs over related billings | | | | | |
Prepare the relevant sections of the ending balance sheet for 2015 under the completed-contract method.
|
Ending Balance Sheet (partial) | |
|
| | | | |
| | | | |
| | | | |
| | | | |
Less: Construction in progress | | | | | |
Provision for loss on contract | | | | | |
Excess of billings and provision for loss over | | | | | |