lorelie has taken over a construction project which is 36% complete .the budget of the work to be done today is $6 millon.The projects planned
lorelie has taken over a construction project which is 36% complete .the budget of the work to be done today is $6 millon.The projects planned duration is 3 years.the total budget of the project is $120 million.The amount spency by the project until today is $6.5 million.what does $6 million represernt :earned value,actual cost,Planned value.