Louie Beton (LB) ABC Problem Louie Beton (LB) is a designer of high-quality bags and purses. Each design is made in small batches. Each summer,
Louie Beton (LB) ABC Problem Louie Beton (LB) is a designer of high-quality bags and purses. Each design is made in small batches. Each summer, LB comes out with new designs for the bag and purse. The company changes these designs every year. The bags are all made on the same fabrication equipment that is expected to operate at capacity., The equipment must be switched over to a new design and set up to prepare to produce each new batch of products. When completed, each batch of products is immediately shipped to a wholesaler Shipping costs vary with the number of shipments. Budgeted for costs and activities for the year ending 2019 is as follows:
Direct materials - purses P319,155
Direct materials bags 454,995
Direct manufacturing labor purses 99,000
Direct manufacturing labor bags 113,000 `
Setup 64,000
Shipping 73,000
Design 169,000
Plant, utilities, and administration 221,000
Additional information:
BAGS PURSES
Number of products 6,175 3,075
Hours of production 1,665 1,585
Number of batches 120 80
Number of designs 2 2
Additional information:
BAGS PURSES
Number of products 6,175 3,075
Hours of production 1,665 1,585
Number of batches 120 80
Number of designs 2 2
Required:
- Identify the most appropriate cost driver for each category, briefly Explain your choice of cost driver.
- Calculate the budgeted cost per unit of cost driver for each category.
- Calculate the budgeted total cost and cost per unit for each product line. Explain how you can use the information in letter C to reduce costs.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started