Lucea Limited acquired funding from a bank on 1 January 2020 to build a new shopping mall. Construction began on 1 February 2020 and ended
Lucea Limited acquired funding from a bank on 1 January 2020 to build a new shopping mall. Construction began on 1 February 2020 and ended on the 30 November 2020. During the months of September and August work was suspended on the project. The relevant months for the capitalization of interest are: Select one: A. 7 months OB. 8 months OC. 10 months D. 9 months