Question
Mackinaw Inc. processes a base chemical into plastic.Standard costsand actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 4,800
Mackinaw Inc. processes a base chemical into plastic.Standard costsand actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 4,800 units of product were as follows:
Standard Costs Actual Costs
Direct materials 6,200 lb. at $5.20 6,100lb. at $5.10
Direct labor 1,200 hrs. at $17.30 1,230 hrs. at $17.60
Factory overhead Rates per direct labor hr.,
based on 100% of normal
capacity of 1,250 direct
labor hrs.:
Variable cost, $3.00 $3,560 variable cost
Fixed cost, $4.70 $5,875 fixed cost
Each unit requires 0.25 hour of direct labor.
- Required:
- a.Determine the direct materialsprice variance, direct materialsquantity variance, and total direct materialscost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
- Direct materials price variance$
- Direct materials quantity variance
- Total direct materials cost variance$
- b.Determine the direct laborrate variance, direct labortime variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
- Direct labor rate variance $__________
- Direct labor time variance __________
- Total direct labor cost variance $______
- c.Determine variable factory overheadcontrollable variance, the fixed factory overheadvolume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
- Variable factory overhead controllable variance $____
- Fixed factory overhead volume variance _______
- Total factory overhead cost variance $________
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started