Question
Mahaley, Inc., manufactures and sells two products: Product Q9 and Product F0. Data concerning the expected production of each product and the expected total direct
-
Mahaley, Inc., manufactures and sells two products: Product Q9 and Product F0. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below:
Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product Q9 870 8.7 7,569 Product F0 870 6.7 5,829 Total direct labor-hours 13,398 The direct labor rate is $22.50 per DLH. The direct materials cost per unit for each product is given below:
Direct Materials Cost per Unit Product Q9 $175.60 Product F0 $147.40 The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity:
Estimated Expected Activity Activity Cost Pools Activity Measures Overhead Cost Product Q9 Product F0 Total Labor-related DLHs $ 386,680 7,569 5,829 13,398 Machine setups setups 47,330 650 550 1,200 Order size MHs 288,200 3,800 3,600 7,400 $ 722,210 The unit product cost of Product F0 under activity-based costing is closest to: (Round your intermediate calculations to 2 decimal places.)
A. $750.82 per unit
B. $677.62 per unit
C. $526.87 per unit
D. $371.35 per unit
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started