Question

1 Approved Answer

Management in Construction - Estimating Consder a certan activity withn your project with a quantity of 1650m2 Use the following data to estmate the activity

image text in transcribed

Management in Construction - Estimating

Consder a certan activity withn your project with a quantity of 1650m2 Use the following data to estmate the activity duration and cost (Including O\&P) You plan NOT to use the crew D 7 rather a larger crew of 2 workers and 1 helper to speed the job it is noted that using local labor the bare hourly rates for a worker and a helper are $30 and $25 respectively Material cost is also increased 20%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Evaluation Of An Internal Audit Department The Case Of SOTELMA

Authors: Oumar Bah

1st Edition

6204486039, 978-6204486031

More Books

Students also viewed these Accounting questions