Management of Mittel Company would like to reduce the amount of time between when a customer places an order and when the order is shipped.

Management of Mittel Company would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:

Inspection time 0.7 days
Wait time (from order to start of production) 16.4 days
Process time 3.3 days
Move time 0.9 days
Queue time 3.6 days

Required:

  1. Compute the throughput time.

Note: Round your answer to 1 decimal place.

  1. Compute the manufacturing cycle efficiency (MCE) for the quarter.

Note: Round your percentage answer to nearest whole percent.

  1. What percentage of the throughput time was spent in nonvalue-added activities?

Note: Round your percentage answer to nearest whole percent.

  1. Compute the delivery cycle time.

Note: Round your intermediate calculations and final answer to 1 decimal place.

  1. If by using Lean Production all queue time during production is eliminated, what will be the new MCE?

Note: Do not round intermediate calculations. Round your percentage answer to 1 decimal place.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Auditing And Assurance Services

Authors: Philomena Leung, Paul Coram, Barry J. Cooper, Peter Richardson

6th Edition

1118615247, 9781118615249

More Books

Students also viewed these Accounting questions