Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The
Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below
- Determine the optimum cycle time (i.e., actual operating time/desired output).
- What is the minimum number of stations needed?
- Assign tasks to workstations.
- What is the efficiency of this assembly line?
Task | Time (min.) | Immediate Follower |
a | .2 | b,d |
b | .2 | f |
c | .4 | b,e |
d | .1 | e |
e | .3 | f |
f | .2 | h |
g | .1 | h |
h | .2 | i |
i | .6 | none |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started