Question

1 Approved Answer

Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for bolts of cloth. The figures are in hundreds of

Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for bolts of cloth. The figures are in hundreds of bolts. The department has a regular output capacity of 270(00) bolts per month, except for the seventh month, when capacity will be 245(00) bolts. Regular output has a cost of $25 per hundred bolts. Workers can be assigned to other jobs if production is less than regular. The beginning inventory is zero bolts. Month 1 2 3 4 5 6 7 Total Forecast 300 250 250 320 280 275 250 1,925 a. Develop a chase plan that matches the forecast and compute the total cost of your plan. Overtime is $65 per hundred bolts. Regular production can be less than regular capacity. (Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required.)

Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for bolts of cloth. The figures are in hundreds of bolts. The department has a regular output capacity of 270(00) bolts per month, except for the seventh month, when capacity will be 245(00) bolts. Regular output has a cost of $25 per hundred bolts. Workers can be assigned to other jobs if production is less than regular. The beginning inventory is zero bolts.

Month 1 2 3 4 5 6 7 Total
Forecast 300 250 250 320 280 275 250 1,925

a. Develop a chase plan that matches the forecast and compute the total cost of your plan. Overtime is $65 per hundred bolts. Regular production can be less than regular capacity. (Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required.)

Periods: 1. 2 3 4 5 6 7 Total

Forecast 300 250 250 320 280 275 250 1925

Output

Regular:

Overtime

Output Forcast

Cost

Regular

Overtime

Total

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To develop a chase plan and compute the total cost for the production forecast we need to adjust production levels to match the forecast demand while ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

An Introduction To Project Management With A Brief Guide To Microsoft Project 2016

Authors: Kathy Schwalbe

6th Edition

1544701896, 978-1544701899

More Books

Students also viewed these General Management questions