Maneet is building her project schedule by creating dependencies between activities. Which of the following must she define for each dependency? the predecessor activity's scheduled
Maneet is building her project schedule by creating dependencies between activities. Which of the following must she define for each dependency? the predecessor activity's scheduled start date when resources work on activities the successor activity's scheduled finish date predecessors and successors