Many services maintain records of sales noting:A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -

Many services maintain records of sales noting:A network consists of the following list. Times are given in weeks.
Activity
Preceding
Optimistic
Probable
Pessimistic
A
--
5
11
14
B
-
3
3
9
C
--
6
10
14
D
A, B
3
5
7
E
B
4
6
11
F
C
6
8
13
G
D, E
2
4
6
H
F
3
3
9
a. Draw the network diagram.
b. Calculate the expected duration and variance of each activity.
c. Calculate the expected duration and variance of the critical path.
d. Calculate the probability that the project will be completed in less than 28 weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Concepts

Authors: Frank Rothaermel

2nd edition

77645065, 1259384071, 9780077645069, 978-1259384073

More Books

Students also viewed these General Management questions

Question

How buffering can improve performance of a computer system

Answered: 1 week ago

Question

Write the importance of mitochondria in a cell?

Answered: 1 week ago