Marcus is the project manager of the CAC implementation project and to reduce the risk of the CAC product not being delivered on time, he
Marcus is the project manager of the CAC implementation project and to reduce the risk of the CAC product not being delivered on time, he has written penalties into the vendor contract. For each day that the product delivery is delayed, payment for the product will be reduced by 3%. Marcus is using what response to a potential risk event