Question

1 Approved Answer

Marle Construction enters into a contract with a customer to build a warehouse for $550,000 on March 30, 2015 with a performance bonus of $50,000

Marle Construction enters into a contract with a customer to build a warehouse for $550,000 on March 30, 2015 with a performance bonus of $50,000 if the building is completed by July 31, 2015.The bonus is reduced by $10,000 each week that completion is delayed.Marle commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes:

Completed by Probability
July 31, 2015 70%
Delay 1 week 20%
Delay 2 weeks 10%

The transaction price for this transaction is:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audits

Authors: Arthur E Cutforth

1st Edition

1017097445, 978-1017097443

More Books

Students also viewed these Accounting questions

Question

b. Where did they come from?

Answered: 1 week ago

Question

c. What were the reasons for their move? Did they come voluntarily?

Answered: 1 week ago

Question

5. How do economic situations affect intergroup relations?

Answered: 1 week ago