Mass Balance company is manufacturing a new digital scale for use by a large chemical company. The order is 40 units. The first scale took
- Mass Balance company is manufacturing a new digital scale for use by a large chemical company. The order is 40 units. The first scale took 60 hours of Direct Labor.Learning rate is 80%.
- What is the estimated time for the 40th unit?
- What is the estimated total time for producing all 40 units?
COST ACCOUNTING \ LEARNING CURVEANALYSIS