Match the following terms to the correct definition. - - The last point at which a project activity must begin in order to not delay

Match the following terms to the correct definition.
--
The last point at which a project activity must begin in order to not delay the project completion.
--
The soonest a project activity can begin based on predecessor completion times.
--
The soonest a project activity can be completed based on predecessor completion times and activity duration.
--
The last point at which a project activity must be completed in order to not delay the project completion.
--
The amount of time a project activity can be delayed without delaying the project completion.
1.
Earliest Start Time
2.
Latest Start Time
3.
Earliest Finish Time
4.
Slack Time
5.
Latest Finish Time

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Analytics Methods Models And Decisions

Authors: James R. Evans

2nd Edition

321997824, 978-1119298588, 978-0321997821

More Books

Students also viewed these General Management questions