Question
1 Approved Answer
Material delays have routinely limited production of household sinks to 4 0 0 units per day. If the plant efficiency is 8 0 % ,
Material delays have routinely limited production of household sinks to units per day. If the plant efficiency is then its effective capacity enter your response here sinks per day round your answer to the nearest whole number