Question
Materials Variances Assume that Pearle Vision uses standard costs to control the materials in its made-to-order sunglasses. The standards call for 2 ounces of material
Materials Variances Assume that Pearle Vision uses standard costs to control the materials in its made-to-order sunglasses. The standards call for 2 ounces of material for each pair of lenses. The standard cost per ounce of material is $15.75. During July, the Santa Clara location produced 5,200 pairs of sunglasses and used 9,600 ounces of materials. The cost of the materials during July was $16.50 per ounce, and there were no beginning or ending inventories.
Required a. Determine the flexible budget materials cost for the completion of the 5,200 pairs of glasses. $Answer
b. Determine the actual materials cost incurred for the completion of the 5,200 pairs of glasses and compute the total materials variance. $Answer
actual materials cost
$Answer
total materials variance
c. How much of the total variance was related to the price paid to purchase the materials? $Answer
d. How much of the difference between the answers to requirements (a) and (b) was related to the quantity of materials used?
$Answer
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started