Question

1 Approved Answer

Max 2 0 0 D R B + 2 8 0 D R W s . t . 2 0 D R B + 2

Max 200DRB+280DRW
s.t.
20DRB+25DRW40,000 Steel available
40DRB+100DRW120,000 Manufacturing minutes
60DRB+40DRW96,000 Assembly minutes
,DRB,DRW0
The computer solution is shown in Figure 3.20.
a. What are the optimal solution and the total profit contribution?
b. Another supplier offered to provide Deegan Industries with an additional 500 pounds of the steel alloy at $2 per fiund. Should Deegan purchase the additional pounds of the steel alloy? Explain.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Analytics Methods Models And Decisions

Authors: James R. Evans

2nd Edition

321997824, 978-1119298588, 978-0321997821

More Books

Students also viewed these General Management questions