Question

1 Approved Answer

MAY WP Budget Technique Actual Start Actual Finish MAR APR 1.2.2.1 $10,000 Fixed Formula (50/50) 15 MAR 15 APR 1.2.2.2 $20,000 Percent Complete 01 APR

image text in transcribed

MAY WP Budget Technique Actual Start Actual Finish MAR APR 1.2.2.1 $10,000 Fixed Formula (50/50) 15 MAR 15 APR 1.2.2.2 $20,000 Percent Complete 01 APR 21 APR 1.2.2.3 $16,000 Fixed Formula (0/100) 15 MAR 15 MAY Monthly Earned Value ? ? ? Cumulative Earned Value Figure 1. Earned Value Metrics for Work Packages 1.2.2.1, 1.2.2.2, 1.2.2.3 Consider the earned value data presented in Figure 1. Based on the information presented, what is the total monthly earned value for the month of March? $5,000 a. O b. $10,000 $16,000 . Od $20,000 MAY WP Budget Technique Actual Start Actual Finish MAR APR 1.2.2.1 $10,000 Fixed Formula (50/50) 15 MAR 15 APR 1.2.2.2 $20,000 Percent Complete 01 APR 21 APR 1.2.2.3 $16,000 Fixed Formula (0/100) 15 MAR 15 MAY Monthly Earned Value ? ? ? Cumulative Earned Value Figure 1. Earned Value Metrics for Work Packages 1.2.2.1, 1.2.2.2, 1.2.2.3 Consider the earned value data presented in Figure 1. Based on the information presented, what is the total monthly earned value for the month of March? $5,000 a. O b. $10,000 $16,000 . Od $20,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Literacy For Managers

Authors: Richard A. Lambert

1st Edition

1613630182, 978-1613630181

More Books

Students also viewed these Finance questions