Megah Teraju Sdn Bhd manufactures cooling system products. Megah Teraju produces all the parts necessary for its products except for one electronic component, which is
Megah Teraju Sdn Bhd manufactures cooling system products. Megah Teraju produces all the parts necessary for its products except for one electronic component, which is purchased from three local suppliers: Iman Enterprise, Ihsan Sdn Bhd and Ikhlas Berhad. All suppliers are reliable and seldom cause late delivery. Several activities related to the supply of electronic component along with activity driver have been identified. The following is the information on the Companys activity rates in 2021:
Activity | Cost Per Unit (RM) |
Wastage time due to low quality of electronic component | RM 100/re-work unit |
Electronic component order | RM 300/order |
Order received | RM 150/delivery |
Checking order received | RM 200/delivery |
Return of electronic component to supplier | RM 50/return |
Payment to supplier | RM 250/invoice |
Invoice amount dispute | RM 500/dispute |
Information on the involvement of customer-related activities by the suppliers for year 2021 is as follows:
| Iman Enterprise | Ihsan Sdn Bhd | Ikhlas Berhad |
Wastage time due to low quality of electronic component | 20 | 0 | 4 |
Electronic component order | 80 | 96 | 60 |
Order received | 80 | 120 | 76 |
Checking order received | 80 | 120 | 76 |
Return of electronic component to supplier | 10 | 8 | 30 |
Payment to supplier | 24 | 96 | 24 |
Invoice amount dispute | 4 | 0 | 26 |
A purchasing manager with an annual salary of RM100,000 was hired. It is estimated that 60% of his time is used to manage the supply from Ihsan Sdn Bhd and the remaining 40% of his time is used equally to manage the other two suppliers namely Iman Enterprise and Ikhlas Berhad. The costs of purchasing raw materials from each supplier are as follows:
Iman Enterprise | RM 200,000 |
Ihsan Sdn Bhd | RM 250,000 |
Ikhlas Berhad | RM 80,000 |
a) Based on the activities related to the suppliers listed, identify THREE (3) nonvalue added activities and suggest appropriate actions to be taken by Megah Teraju Sdn Bhd.
b) Other than measuring cost of supplier using the supplier performance index as calculated above, there are also other criteria to measure supplier performance. Discuss TWO (2) of these criteria and their respective measures to measure the supplier performance.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started