Melbourne Company estimated that machine hours for the year would be 40,000 hours and overhead (all foed) would be $320,000 Melbourne applies is overhead on
Melbourne Company estimated that machine hours for the year would be 40,000 hours and overhead (all foed) would be $320,000 Melbourne applies is overhead on the basis of machine hours. During the year all overhead costs were exactly as planned $320,000). There was $44.000 in overapplied overhead Required How many machine-hours were worked during the period? Machine hours