MGMT 335 1. Cardinal Inc. makes a variety of electronic products. Its camera manufacturing plant is considering choosing between two different processes named Alpha and

MGMT 335 1. Cardinal Inc. makes a variety of electronic products. Its camera manufacturing plant is considering choosing between two different processes named Alpha and Beta, which can be used to make two component parts A and B. To make the correct decision, the managers would like to compare the multi-factor productivity of process Alpha with that of process Beta. The value of process output for component A and B are $175 and $150 per unit, respectively. The corresponding overhead cost is $6,000 for Alpha process and $5,000 for Beta process. The table below presents detailed information. Process Alpha Process Beta Product A Product B Product A Product B Output (units) 50 60 30 80 Labor ($) $1200 $1400 $1000 $2000 Material ($) $2500 $3000 $1500 $3500 Please answer the following questions: a. Please compute the multifactor productivity for process Alpha and Beta. Which process, Alpha or Beta, is more productive? Which one would you recommend? b. If the company chooses the process you recommend, how much increase in productivity (in percentage) the company will get?

2. Below is the table which includes the information of a new project of ABC Inc. The deterministic time for each activity (from activity A to activity G) is in the table. Table 1. Activity Immediate Predecessor(s ) Time (Weeks) A --- 2 B A 1 C A 3 D B 7 E B, C 3 F C 6 G D, E, F 4 Please answer the following questions: 1) Draw the network of the project corresponding to the information of Table 1. 2) Which path is the critical path? What is the length of the expected time of the project? 3) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. Please complete the table below. Table 2.

Activit y Earlies t Start Earlies t Finish Latest Start Latest Finish Slack A B C D E F G

Extra credit 3. Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow. Activity Descriptio n Immediate Predecessor( s) Optimistic (Weeks) Most Likely (Weeks) Pessimisti c (Weeks) A --- 4 7 10 B A 2 8 20 C A 8 12 16 D B 1 2 3 E D, C 6 8 22 F C 2 3 4 G F 2 2 2 H F 6 8 10 I E, G, H 4 8 12 J I 1 2 3 a. Please draw the network of the project. b. What is the expected time and the standard deviation of each path? b. What is the probability of completion of the project before week 42?

Please type your answer and the steps of computation in a Word file. (Please DO NOT just write the answer. Otherwise you will not have full credit. Show the steps that you solve the problems. Partial credit will be given based on your computation steps. Please do not submit PDF files. Please do not insert scanned picture your file.) Please save the file as "MGMT335Midterm_Your First Name_Your Last Name.docx" and submit through Canvas. Please do not submit wrong files. Otherwise, you will not get grade. Due date: June 29, 2023 Thursday 11 PM.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: Cornelius A. De Kluyver

1st Edition

1631570730, 978-1631570735

More Books

Students also viewed these General Management questions