Michelle Inc. has identified the following overhead activities, their budgeted costs and each activitys cost driver: Activity Cost Pool Budgeted Overhead Cost Cost Driver Budgeted
Michelle Inc. has identified the following overhead activities, their budgeted costs and each activitys cost driver:
Activity Cost Pool | Budgeted Overhead Cost | Cost Driver | Budgeted Level for Cost Driver |
Lifting | $30,000 | Number of lifts | 1,200 |
Inspecting | $36,000 | Inspection hours | 2,400 |
Machining | $84,000 | Machine hours | 12,000 |
The company have the following job which was completed this month:
Job 248 | |
Total direct materials | $7,850 |
Total direct labour | $2,450 |
Units completed | 60 |
Number of lifts | 4 |
Inspection hours | 8 |
Machine hours | 40 |
Direct labour hours | 38 |
a) Calculate the activity-based overhead rate for lifts.
b) Calculate the activity-based overhead rate for inspections.
c) Calculate the activity-based overhead rate for machining.
d) Calculate the total cost of Job 248.
e) Assume the company uses the plantwide overhead rate instead, based on direct labour hours. If the total estimated direct labour hours are 12,500 hours, what is the total cost of Job 248 using the plantwide rate?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started