mins ative d. critical help? Why ded i slages completed so far: ullo is developing a social networking app for tablet computers. She has the following or Estimated Cost Stage Completed Actual Cost of of Stage Stage to Date Week 1 Week 2 Week 3 Week 4 500 500 700 50 $500 400 100% 100 % 100 % 50% expedite the 500 400 Not yet begun wekble similar to the one in Figure 3.27 For wvalue (EV) at week 3. lculate the budget at completion (BAC), planned value (PV), atualcostaq and asures of cost variance (CV), schedule variance (SV) hodyle performance index (SPD 3, calculate the performance me 23. Robyn Cucurullo is developing a social networking app for tablet computers. She has the following tive stages completed so far: Estimated Cost Stage Completed Actual Cost of itical p? Why Week or Stage Stage to Date 500 500 700 50 Not yet begun of Stage Week 1 Week 2 Week 3 Week 4 Week 5 $500 400 600 500 400 100 % 100 % 100% 50% 0 dite the a. Create a table similar to the one in Figure 3.27 b. For Week 3, calculate the budget at completion (BAC), planned value (PV), actual cost (AC), and earned value (EV) at week 3. or Week 3, calculate the performance measures of cost variance (CV), schedule variance (SV). the cost performance index (CPI), and the schedule perfo mance index (SPI). d. What can you tell about the budget in Week 3 by using these performance measures? e. What can you tell about the schedule in Week 3 by using these performance measures? f. For Weet 2 mins ative d. critical help? Why ded i slages completed so far: ullo is developing a social networking app for tablet computers. She has the following or Estimated Cost Stage Completed Actual Cost of of Stage Stage to Date Week 1 Week 2 Week 3 Week 4 500 500 700 50 $500 400 100% 100 % 100 % 50% expedite the 500 400 Not yet begun wekble similar to the one in Figure 3.27 For wvalue (EV) at week 3. lculate the budget at completion (BAC), planned value (PV), atualcostaq and asures of cost variance (CV), schedule variance (SV) hodyle performance index (SPD 3, calculate the performance me 23. Robyn Cucurullo is developing a social networking app for tablet computers. She has the following tive stages completed so far: Estimated Cost Stage Completed Actual Cost of itical p? Why Week or Stage Stage to Date 500 500 700 50 Not yet begun of Stage Week 1 Week 2 Week 3 Week 4 Week 5 $500 400 600 500 400 100 % 100 % 100% 50% 0 dite the a. Create a table similar to the one in Figure 3.27 b. For Week 3, calculate the budget at completion (BAC), planned value (PV), actual cost (AC), and earned value (EV) at week 3. or Week 3, calculate the performance measures of cost variance (CV), schedule variance (SV). the cost performance index (CPI), and the schedule perfo mance index (SPI). d. What can you tell about the budget in Week 3 by using these performance measures? e. What can you tell about the schedule in Week 3 by using these performance measures? f. For Weet 2