Question
1 Approved Answer
Model 1000 master schedule Week 1 2 3 4 5 6 7 8 9 10 Demand 18 5 12 10 Crankcase 20 25 13
Model 1000 master schedule Week 1 2 3 4 5 6 7 8 9 10 Demand 18 5 12 10 Crankcase 20 25 13 Model 1000 product structure Engine assembly Gear box Lead time 2 weeks Used: 1 per engine Input shaft Lead time 3 weeks Used: 2 per gear box 11 12 6 4 13