Question

1 Approved Answer

Monitoring and Controlling Template Project Title Project Manager Customer Name A. Risk Assessment Risk Description Likelihood (L, M, H) Impact (L, M, H) Responsible Person

Monitoring and Controlling Template

Project Title Project Manager Customer Name

A. Risk Assessment

Risk

Description

Likelihood

(L, M, H)

Impact

(L, M, H)

Responsible Person Prevention/Mitigation Strategy

Key: L=Low, M=Medium, H=High

B. Gantt Chart

C1. Earned Value Analysis

Team EV AC PV CV CPI SV SPI
Total

C2. Earned Value Projections

Team EAC ETC Est. Dur. Est. Completion Date

C3. Discussion of Earned Value Analysis and Projections

D1. Burndown Chart

D2. Discussion of Burndown Chart

E. Mitigation Plan

================================

Case Study 5

Merrilton Mobile Payment Portal

Merrilton is in need of an online payment system. The city government has started a project to create a mobile portal for payments. The city's citizens will use this portal to make payments toward recurring costs for utilities and public housing. It will also allow citizens to pay one-time charges for city code enforcement items or services. The mayor, Talia Thomas, is concerned that the project may take longer than expected and cost more than the allotted budget.

This project integrates three main billing systems into the new payment portal. Each of the three systems needs to be upgraded so integration with the new system is possible. In the past, a citizen might update an address in the utility system, but then a ticket would still be mailed to an old address. Other times, a citizen would be owed a refund of a housing deposit upon moving out of an apartment but were unable to apply that refund to the payment of a final utility bill because the systems did not communicate.

The original labor budget for the project is $105,200, based on 2,104 budgeted hours at the standard IT department rate of $50/hr. Any necessary equipment will be paid for out of a state technology grant program whose funds are expiring this fiscal year.

The project started the first Monday of March, and the goal is to finish by the end of the city's fiscal year, which runs July 1-June 30. The Technology department head, Mei Phan, holds a weekly project status meeting with the mayor on Tuesday mornings.The main focus of the fourth weekly meeting is both on bringing in a new project manager, who is taking over for the original project manager, and on reassuring the mayor that a plan is in place to complete the project successfully.

In preparation for the weekly meeting, each of the team leads has submitted a status report to the Technology department head, showing all work completed and money spent by the end of day 16.

Teams Completed Tasks

Maya Johnson

System Requirements

1.1 Billing department user interviews - day 5

1.2 Functional requirements document - day 8

1.3 Determine technology needs - day 10

Fatima Kalani

Utilities

2.1 Create database tables - day 15

Alex Patel

Code Enforcement

Jack Martin

Public Housing

4.1 Create database tables - day 16

Mateo Costa

Payment Processing

Work Breakdown Structure

The following work breakdown structure (WBS) shows the tasks required to complete the project along with duration estimates and task predecessors. Tasks may be assigned to a single individual or multiple individuals.

Line # WBS # Phases/Tasks Days Predecessors
1 1.0 System Requirements
2 1.1 Billing department user interviews 3
3 1.2 Functional requirements document 3 1.1
4 1.3 Determine technology needs 4 1.1
5 1.4 Establish testing plan 8 1.2, 1.3
6 1.5 Establish implementation plan 5 1.4
7 2.0 Utilities
8 2.1 Create database tables 6 1.3
9 2.2 Data cleanup and import 4 2.1
10 2.3 Customization of utility module 13 2.1
11 2.4 Integration with water meter system 5 2.2, 2.3
12 2.5 Testing 3 2.4
13 3.0 Code Enforcement
14 3.1 GIS system integration 5 1.3
15 3.2 Mobile device procurement 7 1.3
16 3.3 Customization of ticketing module 12 3.1, 3.2
17 3.4 Testing 3 3.3
18 3.5 Hiring and training 15 3.4
19 4.0 Public Housing
20 4.1 Create database tables 6 1.3
21 4.2 Data cleanup and import 6 4.1
22 4.3 Customization of property module 18 1.3
23 4.4 Maintenance request log development 20 1.3
24 4.5 Testing 3 4.2, 4.3, 4.4
25 5.0 Payment Processing
26 5.1 Ad hoc service billing development 22 2.1, 3.1, 4.1
27 5.2 Integration with billing systems 10 2.5, 3.5, 4.5, 5.1
28 5.3 Establish merchant accounts 6 1.5, 5.2
29 5.4 Set up EFT gateway 7 5.3
30 5.5 Training billing specialists 8 5.4

Status Reports

Maya Johnson

Budget % Complete Expenditures
Hours Dollars Hours Dollars
System Requirements 184 $9,200.00 67.13% 136 $6,800.00
Billing department user interviews 24 $1,200.00 100% 32 $1,600.00
Functional requirements document 24 $1,200.00 100% 19 $950.00
Determine technology needs 32 $1,600.00 100% 36 $1,800.00
Establish testing plan 64 $3,200.00 68% 49 $2,450.00
Establish implementation plan 40 $2,000.00 0% 0 -

Notes:

Our work is mostly completed. We have done everything except for finalize some lingering details of the communication plan. Once the system is in place and running, citizens will need to log in using a temporary code in order to set up their account and activate the app. We have been waiting to hear whether we have enough email addresses to send the codes out electronically or if it would be better to include a paper insert in the July utility bills. It seems that either way we will miss some people.

Fatima Kalani

Budget % Complete Expenditures
Hours Dollars Hours Dollars
Utilities 352 $17,600.00 26.23% 90 $4,500.00
Create database tables 48 $2,400.00 100% 45 $2,250.00
Data cleanup and import 65 $1,600.00 54% 15 $750.00
Customization of utility module 208 $10,400.00 13% 30 $1,500.00
Integration with water meter system 40 $2,000.00 0% 0 -
Testing 24 $1,200.00 0% 0 -

Notes:

The database is functioning, and our quality audits show that everything matches with our legacy system. As we discussed the status of the database in our last team meeting, someone had the question of what happens if anyone moves, starts service, or stops service between now and when the system goes live. Do we have an estimate of how many service changes usually happen each month? Depending on how many we usually have, we will develop a recommendation for keeping the databases synchronized until we go live on July 1.

Alex Patel

Budget % Complete Expenditures
Hours Dollars Hours Dollars
Code Enforcement 480 $24,000.00 17.18% 90 $ 4,500.00
GIS system integration 40 $2,000.00 90% 40 $2,000.00
Mobile device procurement 56 $2,800.00 83% 50 $2,500.00
Customization of ticketing module 240 $12,000.00 0% 0 -
Testing 24 $1,200.00 0% 0 -
Hiring and training 120 $6,000.00 0% 0 -

Notes:

We were able to obtain all the mobile scanners and ticket printing hardware. The grant system made it really easy to purchase those. Any additional hardware we might require after July 1 will have to be covered by the city budget though since the technology upgrade grant is ending on June 30. So far, we have spent most of our time figuring out the hardware features, so we have not gotten very deep into the actual coding yet. It seems to have some useful tools, especially the built-in camera that code-enforcement officers can use to document violations with, which is something our officers have never had before.

Jack Martin

Budget % Complete Expenditures
Hours Dollars Hours Dollars
Public Housing 424 $21,200.00 25.81% 107 $5,350.00
Create database tables 48 $2,040.00 100% 41 $2,050.00
Data cleanup and import 48 $2,400.00 4% 6 $300.00
Customization of property module 144 $7,200.00 18% 24 $1,200.00
Maintenance request log development 160 $8,000.00 21% 36 $1,800.00
Testing 24 $1,200.00 0% 0 -

Notes:

It appears we have all the data we need to be compliant with the Department of Housing and Urban Development (HUD) requirements for supplemental housing assistance. Not all residents of the public housing units have their agreements on file. We are working on making a list of residents who either need a new eligibility form completed or who just need to have their form scanned and attached to their account. The new system will be a lot easier for the office staff since it will be completed electronically. The system will not issue resident key cards if anything is out of order, so we have a sort of forced compliance moving forward. We have decided to keep the existing maintenance requests in the current paper filing system for maintenance staff to work through, and only new requests will show up in the new request system. We simply do not have the data entry personnel available to digitize the existing requests.

Mateo Costa

Budget % Complete Expenditures
Hours Dollars Hours Dollars
Payment Processing 664 $33,200.00 6.89% 59 $2,950.00
Ad hoc service billing development 352 $17,600.00 13% 59 $2,950.00
Integration with billing systems 80 $4,000.00 0% -
Establish merchant accounts 48 $2,400.00 0% -
Set up EFT gateway 56 $2,800.00 0% -
Training billing specialists 128 $6,400.00 0% -

Notes:

During our last community council meeting, the suggestion was made to have another form of payment, such as Autojor or Sparkit. Talia Thomas was at that meeting and promised that we would do everything we could to make more payment types available. We have not yet started working on that part of the project, but that will take some time to research the necessary APIs and other requirements before we can decide which service to go with. Is this something that is really necessary to have right now, or can we add this as a feature later?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management An Integrated Approach

Authors: R. Dan Reid, Nada R. Sanders

7th Edition

1119497388, 978-1119497387

More Books

Students also viewed these General Management questions

Question

Differentiate the function. r(z) = 2-8 - 21/2 r'(z) =

Answered: 1 week ago