Moover Construction enters into a contract with a customer to build a warehouse for $900,000 on June 30, 2017, with a performance bonus of $60,000

Moover Construction enters into a contract with a customer to build a warehouse for $900,000 on June 30, 2017, with a performance bonus of $60,000 if the building is completed by October 31, 2017. The bonus is reduced by $20,000 each week that completion is delayed. The contract also states that if the warehouse receives a favorable safety inspection rating from government inspectors by November 30, Moover will receive a performance bonus of $40,000.

Moovercommonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes:

Completed by

Probability

October 31, 2017

35%

November 7, 2017

50%

November 14, 2017

10%

November 21, 2017

5%

In addition, Moover estimates there is a 90% chance that the warehouse will receive a favorable safety inspection rating upon timely completion.

Required:

a- Assume Moover uses the expected value approach. Determine the transaction price for this transaction.

b-Assume Moover uses the most likely amount approach. Determine the transaction price for this transaction.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Company Valuation Playbook Invest With Confidence

Authors: Charles Sunnucks

1st Edition

1838470816, 978-1838470814

Students also viewed these Finance questions