Answered step by step
Verified Expert Solution
Link Copied!

Question

...
1 Approved Answer

More Info Estimated Days Job Painting Assembly Packing Total Task Time Days until Due A 3.5 2.5 1.0 7.0 21 B 7.0 1.0 0.5

image text in transcribedimage text in transcribed

More Info Estimated Days Job Painting Assembly Packing Total Task Time Days until Due A 3.5 2.5 1.0 7.0 21 B 7.0 1.0 0.5 8.5 10 C 7.0 4.0 1.0 12.0 19 D 2.5 2.5 1.5 6.5 15 115 Print Done Consider the following job information. Each job must proceed sequentially through the different work areas, and each area can work on only one job at a time. Sequence the jobs according to the (1) first-come, first-served rule, (2) earliest due date, and (3) critical ratio. Calculate the average lateness under each rule. Which rule performs best? Click the icon to view the job information. (1) The FCFS sequence is A - B - C - D The average job lateness under the FCFS rule is 3.13 days. (Enter your response rounded to two decimal places.) (2) The EDD sequence is A - D - C - B The average job lateness under the EDD rule is 0.63 days. (Enter your response rounded to two decimal places.) (3) The CR sequence is D - C - B - A The average job lateness under the CR rule is 3.38 days. (Enter your response rounded to two decimal places.) The EDD rule performs best.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Economics

Authors: R. Glenn Hubbard

6th edition

978-0134106243

Students also viewed these General Management questions