Question
Morganton Company makes one product and it provided the following information to help prepare the master budget for its first four months of operations: The
Morganton Company makes one product and it provided the following information to help prepare the master budget for its first four months of operations:
The budgeted selling price per unit is $70. Budgeted unit sales for June, July, August, and
September are 8,400, 10,000, 12,000, and 13,000 units, respectively. All sales are on credit.
Forty percent of credit sales are collected in the month of the sale and 60% in the following month.
The ending finished goods inventory equals 20% of the following months unit sales.
The ending raw materials inventory equals 10% of the following months raw materials pro-
duction needs. Each unit of finished goods requires 5 pounds of raw materials. The raw mate-
rials cost $2.00 per pound.
Thirty percent of raw materials purchases are paid for in the month of purchase and 70% in
the following month.
The direct labor wage rate is $15 per hour. Each unit of finished goods requires two direct
labor-hours.
The variable selling and administrative expense per unit sold is $1.80. The fixed selling and
administrative expense per month is $60,000.
Required:
- What are the budgeted sales for July?
2. What are the expected cash collections for July?
3. What is the accounts receivable balance at the end of July?
4. According to the production budget, how many units should be produced in July?
5. If 61,000 pounds of raw materials are needed to meet production in August, how many pounds
of raw materials should be purchased in July?
6. What is the estimated cost of raw materials purchases for July?
7. If the cost of raw material purchases in June is $88,880, what are the estimated cash disburse-
ments for raw materials purchases in July?
8. What is the estimated accounts payable balance at the end of July?
9. What is the estimated raw materials inventory balance at the end of July?
10. What is the total estimated direct labor cost for July assuming the direct labor workforce is adjusted to match the hours required to produce the forecasted number of units produced?
11. If the company always uses an estimated predetermined plantwide overhead rate of $10 per direct labor-hour, what is the estimated unit product cost?
12. What is the estimated finished goods inventory balance at the end of July?
13. What is the estimated cost of goods sold and gross margin for July?
14. What is the estimated total selling and administrative expense for July?
15. What is the estimated net operating income for July?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started