Moving from right to left in project network calculations determines the Question 18 options: A. latest times activities can begin B. earliest times activities can
Moving from right to left in project network calculations determines the Question 18 options: A. latest times activities can begin B. earliest times activities can be finished C. critical path both A and C are correct A, B, and C are all correct