Moving to another question will save this response Question 24 1.923 points Save Answer You are using a triangular estimate for your project. Abdullah
Moving to another question will save this response Question 24 1.923 points Save Answer You are using a triangular estimate for your project. Abdullah reports that his optimistic estimate is 16 hours, his most likely estimate is 24 hours, and the pessimistic estimate is 65 hours. What is the estimated duration tur Abdulah's activity to be completed for your project? 45 hours 35 hours 10 hours 24 hours Question 24 of 52