MS . 5 3 An office furniture manufacturer needs to calculate material requirements for one of its most popular tables. The graphic above shows the

MS.53 An office furniture manufacturer needs to calculate material requirements for one of its most popular tables. The graphic above shows the bill of material for this item. Below are the MRP tables for the top-level assembly (the Office Table Final Assembly) and one of its sub-assemblies (the Table-Top Assembly):
Office Table Final Assembly 8/18/88/158/228/299/59/129/199/26
Gross Requirements 400200300500700200
Scheduled Receipts
Projected On-Hand Inv. 220
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks)1
Lot Size 150
Table-Top Assembly 8/18/88/158/228/299/59/129/199/26
Gross Requirements
Scheduled Receipts 170
Projected On-Hand Inv. 150
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks)2
Lot Size 30
For the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in the week of 9/19?
For the Office Table above, what are the Planned Order Receipts in the week of 8/8?
For the Table-Top Assembly above, what are the Net Requirements in the week of 9/19?
For the Table-Top Assembly above, what are the Planned Order Releases in the week of 9/5?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Human Resource Management Employees And Employers In Action

Authors: Cynthia Fontelle, Louis Bevoc

1st Edition

1688510249, 978-1688510241

More Books

Students also viewed these General Management questions