Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors

Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 47-week completion date requested by the owner. The Mueller project manager prepared the following project network.

A project network with 10 activities and 14 directed arcs is shown.

Activity Start is connected to activity A.

Activity A is connected to activity B, to activity C, and to activity D.

Activity B is connected to activity F.

Activity C is connected to activity E and to activity F.

Activity D is connected to activity E.

Activity E is connected to activity G and to activity Finish.

Activity F is connected to activity G and to activity H.

Activity G is connected to activity H.

Activity H is connected to activity Finish.

Activity Finish has no arcs directed to other activities.

Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows.

Activity Optimistic Most Probable Pessimistic
A 4 8 12
B 6 7 8
C 6 12 18
D 3 5 7
E 6 9 18
F 5 8 17
G 10 15 20
H 5 6 13

(a)

Find the critical path. (Enter your answers as a comma-separated list.)

(b)

What is the expected project completion time (in weeks)?

weeks

(c)

Based only on the critical path, what is the estimated probability the project can be completed in 47 weeks as requested by the owner? (Round your answer to four decimal places.)

(d)

Based only on the critical path, what is the estimated probability the building project could run more than 3 months late? Use 60 weeks for this calculation. (Round your answer to four decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Ricky W. Griffin

11th edition

111196971X, 978-1111969714

More Books

Students also viewed these General Management questions