Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected
Multiple Versus Single Overhead Rates, Activity Drivers
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:
Activity | Expected Cost | Activity Driver | Activity Capacity |
Setting up equipment | $473,860 | Number of setups | 580 |
Ordering costs | 315,000 | Number of orders | 17,500 |
Machine costs | 799,900 | Machine hours | 42,100 |
Receiving | 401,700 | Receiving hours | 10,300 |
Deoro produces two models of dishwashers with the following expected prime costs and activity demands:
Model A | Model B | |
Direct materials | $589,000 | $847,000 |
Direct labor | $488,000 | $458,000 |
Units completed | 16,900 | 8,600 |
Direct labor hours | 5,400 | 1,900 |
Number of setups | 380 | 200 |
Number of orders | 5,800 | 11,700 |
Machine hours | 24,700 | 17,400 |
Receiving hours | 2,600 | 7,700 |
The company's normal activity is 7,300 direct labor hours.
Required:
1. Determine the unit cost for each model using direct labor hours to apply overhead. Round intermediate calculations and final answers to nearest cent.
Unit Cost | |
Model A | $ |
Model B | $ |
2. Determine the unit cost for each model using the four activity drivers. Round your answers to nearest cent.
Unit Cost | |
Model A | $ |
Model B | $ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started