MY-MLC POSTGRADUATE PROGRAMS OPERATIONS AND SUPPLY CHAIN MANAGEMENT INDIVIDUAL ASSIGNMENT ON ASSEMBLY LINE BALANCING The local university has developed an eight-step process for screening the

MY-MLC

POSTGRADUATE PROGRAMS

OPERATIONS AND SUPPLY CHAIN MANAGEMENT

INDIVIDUAL ASSIGNMENT ON ASSEMBLY LINE BALANCING

The local university has developed an eight-step process for screening the thousands of admissions applications it gets each year. The registrar has decided that the best way to take a first cut at all these applications is by employing a line process. The following table shows the times and predecessors for the various tasks:

REQUIRED:

a)Draw a precedence diagram for the tasks. Suppose the university needs to process 30 applications an hour during the peak season. What is the task time? What is the theoretical minimum number of workstations?

b)Develop workstation assignments by using the "largest eligible task" rule.

c)How many workstations does your solution require? What is the cycle time for the line? What is the idle time? What are the percent idle time and the efficiency delay?

d)In theory, what is the fastest cycle time possible, given the tasks listed above? How many applications per hour does this translate

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes And Supply Chains

Authors: Lee Krajewski, Naresh Malhotra, Larry Ritzman

13th Global Edition

129240986X, 978-1292409863

Students also viewed these Law questions