n March 2019, at 5.30 pm, a hurricane hit several major building in downtown Kingston, Jamaica Among the buildings damaged by the windstorm was a
n March 2019, at 5.30 pm, a hurricane hit several major building in downtown Kingston, Jamaica
Among the buildings damaged by the windstorm was a tall glass tower that a large bank had leased mostly for administrative offices for its 600 employees, but that also had public banking facilities on the lower floors. Because the hurricane hit just after the end of the workday, there was no loss of life, but property damage to the building and its contents was extensive. Since the bank did not own the building, the bank had to arrange for access to the property after the loss through the buildings owners.
Moreover, the city of Kingston was under lots of water and it was labeled imminently dangerous, the banks officers and employees had no access to the building for over a week. During this week the wind and rain caused further damage to the furniture, equipment and valuable papers.
The banks risk manager had made prior arrangements with a disaster recovery facility in a remote location that allowed the bank to use the emergency facilities computers, phones, and fax machines after a disaster., This facility provided workspace for about one third of the banks critical personnel.
The banks risk manager also made arrangements for a shuttle bus service between the loss location and office space available in nearby New Kingston. Employees were not able to retrieve critical papers from the loss site until two weeks after the hurricane struck, by which time the glass windows in the tower had been replaced or boarded over with plywood.
The company had planned to replace all the destroyed furniture, carpeting, and electronic equipment as well as repaint its entire premises before reoccupying the damaged property. While the building was unusable the bank had to find and rent alternate locations for many of its employees. It also had to continue the expensive shuttle service to New Kingston and to provide many employees with an allowance for their commuting expense. In addition, the bank experienced much inefficiency such as the inability to hold needed conferences and meetings that would normally have taken place in the damaged location. Perhaps the greatest complication arose when the building owner declared that it was too expensive to repair the building and therefore it was terminating all the leases. Leasing the same amount of space in a new location would likely cost the bank about twice what it had been paying at the damaged location.
Based on the information provided you are to complete the following questions.
(1) Identify all the direct losses the bank experienced (10 marks)
(2) Identify all the indirect losses the bank experienced (10 marks)
(3) In a maximum probable loss event arising from a hurricane, identify the additional losses that you would expect (10 marks)
(4) How could the banks risk manager use each of the following risk management tools in this case (5 marks)
(a) Risk assumption
(b) Loss prevention
(c) Loss reduction
(d) Insurance
(e) Risk transfer
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started