n the following project assume that a worker works 4 hours ever day for 5 days a week. In which week minimum resource is required?
n the following project assume that a worker works 4 hours ever day for 5 days a week. In which week minimum resource is required? Activity Duration Predecessor A 5 days -- B 4 days A C 5 days A D 6 days B E 6 days C, D F 6 days E Select one: a. Week 4 b. Week 2 c. Week 6 d. Week 3 e. Week 5