Nadeem BSC Civil engineering Company Nadeem BSC is a civil engineering company. It started work on to civil engineering projects during the year ended 31
Nadeem BSC Civil engineering Company
Nadeem BSC is a civil engineering company. It started work on to civil engineering projects during the year ended 31 December 2020. The nature of both contracts is that the customer controls the asset as the project goes forward. Work is certified by a surveyor as performance obligations are completed. The following figures relate to those projects at the end of the reporting period.
Contract Price
Costs incurred to date Estimated costs to completion Value of work certified to date Progress billing
Qadim Bypass
BD000 18,000 2,800 11,200 5,600 5,200
Hidd Mall
BD000 16,000 5,800 10,400 6,000 6,800
An old disused oil well has been discovered under the site for the Hidd Mall and the costs of dealing with this have been taken into account in the calculation of estimated costs to completion. Nadeem BSCs lawyers are reasonably confident that the customer will have to bear the additional costs which will be incurred in stabilising the land. If negotiations are successful, then the contract price will increase to BD10 million.
Nadeem BSC recognises revenues and profits on civil engineering contracts on the basis of work certified to date.
Required
Calculate the figures which would appear in Nadeem BSCs financial statements in respect of these two projects.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started