Question 1. An assembly line with 8 tasks is to be balanced. The longest task is 12 minutes,
and the total time for all tasks is 48 minutes. The line will operate for 480 minutes per day.
Round up your answers to the nearest whole number (40 points, 10 points each). See
Lecture M4-2 for details.
Question 2. A manager wants to assign tasks to workstations as efficiently as possible. Part A:
Using the following precedence diagram to complete the table with # of following task,
positional weight for nodes g,h and i and Time (Time is in minutes).(Part A: 45 points, 5 points
each)
B. What is the total time for all tasks? (5 points)
C. If the line operates 480 minutes a day, what is the maximum output, round your answer
down to the nearest whole number. (10 points)?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

More Books

Students also viewed these General Management questions