Nash Corporation manufactures and sells custom snowmobiles. From the time an order is placed till the time the snowmobile reaches the customer averages 50 days.
Nash Corporation manufactures and sells custom snowmobiles. From the time an order is placed till the time the snowmobile reaches the customer averages 50 days. This 50 days is spent as follows:
Wait time: 10 days
Move time: 5 days
Process time: 15 days
Queue time: 15 days
Inspection time: 5 days
What is Nash's manufacturing cycle efficiency (MCE) for its snowmobiles?
30.0% | ||
37.5% | ||
40.0% | ||
60.0% |