Need help in creating and AoN diagram (Activity of Node). This is a Project Management Assignment. The activity table is provided below with all the
Need help in creating and AoN diagram (Activity of Node). This is a Project Management Assignment. The activity table is provided below with all the details.
Include the ES (early start), EF (early finish), LS (late start), LF (late finish), and Slack in each work package box, as well as the total project duration and clearly identify the critical path.
Work package Duration Predecessors (days) 1.1 Demolition: remove all old appliances, 2 None cabinets, and flooring 1.2 Demolition: haul away all materials/debris 1.1 2.1 Order cabinets 2 1.2 2.2 Order sink/faucet 1.2 2.3 Order appliances 1.2 2.4 Order paint 1.2 3.1 Create countertop subcontract 2.1 & 2.2 3.2 Create tile subcontract 2.3 3.3 Create painting subcontract 2.4 4.1 Install cabinets 3.1 4.2 Install countertop 3.2 & 4.1 4.3 Install tile floors 4.2 4.4 Install sink/faucet 4.3 4.5 Install appliances 3.3 & 4.3 5.1 Paint walls & ceiling 4.4 & 4.5 6.1 PM Inspection/punchlist 5.1 6.2 Walk through / acceptance 6.1Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started