Question
Need help with accounting work, please provide work in detail. thanks. Chapter 18 Pr. 3. Long-term construction project accounting. Dobson construction specializes in the construction
Need help with accounting work, please provide work in detail. thanks.
Chapter 18
Pr. 3. Long-term construction project accounting.
Dobson construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the typical project lasting fifteen to twenty-four months. The contractor uses the percentage-of completion method of revenue recognition since, given the characteristics of the contractor?s business and contracts, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. Dobson began work on a lump-sum contract at the beginning of 2015. As bid, the statistics were as follows
Lump-sum price (contract price) 4,000,000
Estimated costs
Labor$ 850,000
Materials and subcontractor 1,750,000
Indirect costs400,0003,000,000
$1,000,000
At the end of the first year, the following was the status of the contract:
Billings to date$2,250,000
Costs incurred to date
Labor$ 464,000
Materials and subcontractor 648,000
Indirect costs184,0001305,000
Latest forecast total cost 3,000,000
It should be noted that included in the above costs incurred to date were standard electrical and mechanical materials stored on the job site, but not yet installed, costing $105,000. These costs should not be considered in the costs incurred to date.
Instruction
aCompute the percentage of completion on the contract at the end of 2015
bIndicate the amount of gross profit that would be reported on this contract at the end of 2015.
cMake the journal entry to record the income (loss) for 2015 on Dobson's books.
dIndicate the account(s) and the amount(s) that would be shown on the balance sheet of Dobson Construction at the end of 2015 related to its construction accounts. Also indicate where these items would be classified on the balance sheet. Billings collected during the year amounted to $1,900,000.
e(e) Assume the latest forecast on total costs at the end of 2015 was $4,060,000. How much income (loss) would Dobson report for the year 2015?
Chapter 18 Pr. 3. Long-term construction project accounting. Dobson construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the typical project lasting fifteen to twenty-four months. The contractor uses the percentage-of completion method of revenue recognition since, given the characteristics of the contractor's business and contracts, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. Dobson began work on a lump-sum contract at the beginning of 2015. As bid, the statistics were as follows Lump-sum price (contract price) Estimated costs Labor Materials and subcontractor Indirect costs 4,000,000 $ 850,000 1,750,000 400,000 3,000,000 $1,000,000 At the end of the first year, the following was the status of the contract: Billings to date Costs incurred to date Labor Materials and subcontractor Indirect costs Latest forecast total cost $2,250,000 $ 464,000 648,000 184,000 1305,000 3,000,000 It should be noted that included in the above costs incurred to date were standard electrical and mechanical materials stored on the job site, but not yet installed, costing $105,000. These costs should not be considered in the costs incurred to date. Instruction a Compute the percentage of completion on the contract at the end of 2015 b Indicate the amount of gross profit that would be reported on this contract at the end of 2015. c Make the journal entry to record the income (loss) for 2015 on Dobson's books. d Indicate the account(s) and the amount(s) that would be shown on the balance sheet of Dobson Construction at the end of 2015 related to its construction accounts. Also indicate where these items would be classified on the balance sheet. Billings collected during the year amounted to $1,900,000. e (e) Assume the latest forecast on total costs at the end of 2015 was $4,060,000. How much income (loss) would Dobson report for the year 2015Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started