Question
Need perfect soluton: if you are expert in makig CPM diagram , then take the question , other wise do not waste my question ,
Need perfect soluton: if you are expert in makig CPM diagram , then take the question , other wise do not waste my question , its humble request. this is all information, provided . no more information , its all information
Your team, after performing some additional analysis, came up with the following plan to complete the Sensor Payload Integration delivery order.
- Perform independent research on each of the five candidate IR sensors (2 weeks each for the Red-Eye series, one week each for the others).
- Perform a trade study to down select to two IR sensor candidates (1.5 weeks).
- Develop performance models for both IR sensor candidate sensors (6 weeks each). Note: These should be done separately but can be accomplished in parallel.
- Develop a CONOPS to determine how IR / optical sensors are to be used on the X-65B (8 weeks).
- Use the CONOPS and IR sensor performance models to develop / run independent performance simulations (4 weeks each). Note: These should be done separately but can be accomplished in parallel.
- Use the outcome of your simulations as an input for a technical review to down select to a single IR sensor (preparations 2 weeks).
- Hold the IR sensor review and down select to a single IR sensor (1 day)
- Perform research on the Eagle-Eye 2000 optical sensor (4 weeks).
- Develop a performance model for the Eagle-Eye 2000 (2 weeks).
- UpdatetheperformancemodelfortheTiger-Eye1000opticalsensor(1day).
- Use the CONOP Sand performance models to develop/run independent performance simulations (Tiger-Eye1000-2weeks, Eagle-Eye 2000 - 5 weeks)
- Use the outcome of your simulations as an input for a technical review to down select to a single optical sensor (preparations 2 weeks).
- Hold the optical sensor review and down select to a single optical sensor (1 day). Please note that the IR sensor review, and optical sensor review must be held separately but can occur in parallel.
- Design a common prototype hardware integration package to allow the selected IR/optical sensor to be mounted In the X- 65B. This mounting package must be designed in such a way to mount either the selected IR or optical sensor (dual use) (10 weeks). Note: This includes the development of a prototype to be used for hardware integration package testing (item15).
- Test the hardware integration package and make required modifications(2weeks).
- Build three hardware Integration packages(2weekstotal).
- Design software to integrate the selected IR sensor with theX-65B mission computer(12weeks).
- Code IR sensor integration software(4weeks).
- PerformIRsensorsoftwareintegrationtestingwiththeIRsensorandtheX-65Bs
- DesignsoftwaretointegratetheselectedopticalsensorwiththeX-65Bmissioncomputer(13weeks).
- Code optical sensor integration software(2weeks).
- Perform optical sensor software integration testing with the optical sensor and theX-65B simulator(3weeks).
- Install IR and optical sensors on theX-65B(2dayseachthis can be done simultaneously, if required).
- Perform final IR payload integration testing with theX-65B aircraft and make required changes(2weeks).
- Perform final optical payload integration testing with theX-65B aircraft and make required changes(2weeks).
- Develop test plan forX-65B live sensor testing (sensor independentnot dependent on selected sensors) (12weeks).
- Using the test plan, perform required hazard/safety analysis(3weeks).
- After completing the hazard/safety analysis, attain live sensor testing approval(6weeks).
- PerformX-65B live sensor tests (both sensors simultaneously) (2weeks).
- Develop live demonstration*plan, based on the outcome of theX-65B live sensor tests(1week).
- Make final changes to sensor payload configurations, based on live sensor tests(2weeks).
- Hold live demonstration*review (everything must be ready before this review occurs) (2days).
- Perform a practice series of dry run demos in preparation for the formal demonstration*(1week).
- *Perform live sensor demonstration(1day).
- Performhotwashmeeting after demonstration(1day).
- Write final close-out report, based on hot wash meeting(1week).
*These activities are all referring to the same demonstration.
a. Use the provided CPM Network** to complete the following:
- Critical path
- Node numbers
- Durations
- Earliest / Latest start and finish for each activity
- Float for each activity
- Major milestones***
- Total time to complete this delivery order
***Note[3]: A milestone is a significant point in the project. Highlighted at the event (node), a milestone is often identified after the completion of a major event (review, submission of a significant deliverable, completion of a major test/demonstration, ...). It is a point where the Project Manager assesses the current state of the project before progressing forward.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started